Free Sales Ending Soon – 100% Valid PgMP Exam Dumps with 455 Questions [Q223-Q237]

Free Sales Ending Soon – 100% Valid PgMP Exam Dumps with 455 Questions [Q223-Q237]

Rate this post

Free Sales Ending Soon – 100% Valid PgMP Exam Dumps with 455 Questions

Verified PgMP dumps Q&As on your PMI Certification Exam Questions Certain Success!

Exam Details

After completing the first evaluation (a panel review), you can proceed with registering for the second evaluation, which is a written exam. The qualifying test for the PMI PgMP certification contains 170 multiple-choice questions, including 20 unscored items. The unscored question won’t affect the final score. The students are given 4 hours for passing their exam. The test is administered in the English language at the authorized Pearson VUE centers. You can check the available canter located near you on its official website.

The cost of the PgMP certification exam is $800 for the PMI members and $1000 for those without any membership arrangement. For a retake, a candidate will be paying $600 if he or she is a member and $800 if he or she is not a member. Retaking the test is possible only twice within one year.

 

NO.223 Terri is the program manager for her organization and she’s working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

 
 
 
 

NO.224 As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

 
 
 
 

NO.225 Who makes Go/No-Go decisions during phase gate reviews?

 
 
 
 

NO.226 An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.
In what phase is the risk management plan created?

 
 
 
 

NO.227 You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete.
What should you do next in regard to the vendor’s invoice?

 
 
 
 

NO.228 You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time.
What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

 
 
 
 

NO.229 Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?

 
 
 
 

NO.230 You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

 
 
 
 

NO.231 A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time.
Based on this information which type of performing is present in this scenario?

 
 
 
 

NO.232 You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

 
 
 
 

NO.233 A sponsor decides that the business environment is unfavorable for continuation of a program. The sponsor asks that the program be closed.
What items should be completed as part of the program’s final report?

 
 
 
 

NO.234 All of the following are benefits of a program except for which one?

 
 
 
 

NO.235 What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?

 
 
 
 

NO.236 A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

 
 
 
 

NO.237 What percentage of communication is nonverbal?

 
 
 
 

PgMP Exam Dumps – 100% Marks In PgMP Exam: https://www.trainingdump.com/PMI/PgMP-practice-exam-dumps.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below