NO.37

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

 
 
 
 

NO.38 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Present worth calculations is represented by which of the following equations?

 
 
 
 

NO.39

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost of manufacturing labor for the piece of equipment today?

 
 
 
 

NO.40 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
A cyclical process model was chosen as the basis for total cost management (TCM) because:

 
 
 
 

NO.41 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.
There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.
The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If $10,000 is scheduled to be paid out 5 years from now, what is the minimum amount we can invest today?

 
 
 
 

NO.42

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.

 
 
 
 

NO.43 A schedule’s late dates are calculated during the:

 
 
 
 

NO.44 Which of the following best describes the concept of total cost management:

 
 
 
 

NO.45 ____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.

 
 
 
 

NO.46 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following methods a used for creating critical path schedules:

 
 
 
 

NO.47 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

 
 
 
 

NO.48 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)?

 
 
 
 

NO.49 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
When analyzing a precedence diagram schedule, the “backward pass”

 
 
 
 

NO.50 The process of stating goals and determining the most effective way of reaching them is the definition for:

 
 
 
 

NO.51

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:

 
 
 
 

NO.52 If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

 
 
 
 

NO.53 In a fixed price contract the:

 
 
 
 

NO.54 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow’s hierarchy of needs.

 
 
 
 

NO.55 Some of the principles of good communication are:

 
 
 
 

NO.56 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What class of estimate is used for the preliminary design phase of a project?

 
 
 
 

NO.57

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?

 
 
 
 

Topics of AACE-International CCP: Certified Cost Professional (CCP) Exam

It is suggested that candidates utilize this and/or additional resources, including CCP exam dumps, to obtain background knowledge on the examination topics. Whenever feasible. The AACE-International CCP: Certified Professional Cost Examination curriculum is provided below with details of each part and subjects.

The Certified Cost Professional exam is a much wanted and difficult test. The examination may be intimidating if you are not properly prepared. The CCP examination comprises a closed-book examination, examines 4 modules and takes up to 120 questions. The CCP exam has two parts: the multiple-choice test and the 2,000 word research report. You must achieve the minimum total score of 70 percent to pass the test. The four modules examined for your CCP exam are:

  1. Basic abilities and expertise in cost engineering
  2. Analysis economics
  3. Management of the project
  4. Estimation and management of costs

Regarding your technical document, which is mandatory for registering for the Certified Cost Professional Examination (CCP), your trainers will advise you on suitable subjects and help you develop a solid foundation. They will also assess your work and offer comments when ready. The teachers will also verify that your paper is prepared in accordance with AACE criteria so that the examining body of AACE approves it.

Kryterion acts as a certified test proof for the Certified Cost Professional (CCP) exam with testing sites throughout the globe. You may take your computer-based test every day and whenever you want.

 

Updated Verified CCP Q&As – Pass Guarantee: https://www.trainingdump.com/AACE-International/CCP-practice-exam-dumps.html