NO.37

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

 
 
 
 

NO.38 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Present worth calculations is represented by which of the following equations?

 
 
 
 

NO.39

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost of manufacturing labor for the piece of equipment today?

 
 
 
 

NO.40 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
A cyclical process model was chosen as the basis for total cost management (TCM) because:

 
 
 
 

NO.41 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.
There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.
The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If $10,000 is scheduled to be paid out 5 years from now, what is the minimum amount we can invest today?

 
 
 
 

NO.42

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.

 
 
 
 

NO.43 A schedule’s late dates are calculated during the:

 
 
 
 

NO.44 Which of the following best describes the concept of total cost management:

 
 
 
 

NO.45 ____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.

 
 
 
 

NO.46 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following methods a used for creating critical path schedules:

 
 
 
 

NO.47 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

 
 
 
 

NO.48 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)?

 
 
 
 

NO.49 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
When analyzing a precedence diagram schedule, the “backward pass”

 
 
 
 

NO.50 The process of stating goals and determining the most effective way of reaching them is the definition for:

 
 
 
 

NO.51

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:

 
 
 
 

NO.52 If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

 
 
 
 

NO.53 In a fixed price contract the:

 
 
 
 

NO.54 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow’s hierarchy of needs.

 
 
 
 

NO.55 Some of the principles of good communication are:

 
 
 
 

NO.56 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What class of estimate is used for the preliminary design phase of a project?

 
 
 
 

NO.57

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?

 
 
 
 

Topics of AACE-International CCP: Certified Cost Professional (CCP) Exam

It is suggested that candidates utilize this and/or additional resources, including CCP exam dumps, to obtain background knowledge on the examination topics. Whenever feasible. The AACE-International CCP: Certified Professional Cost Examination curriculum is provided below with details of each part and subjects.

The Certified Cost Professional exam is a much wanted and difficult test. The examination may be intimidating if you are not properly prepared. The CCP examination comprises a closed-book examination, examines 4 modules and takes up to 120 questions. The CCP exam has two parts: the multiple-choice test and the 2,000 word research report. You must achieve the minimum total score of 70 percent to pass the test. The four modules examined for your CCP exam are:

  1. Basic abilities and expertise in cost engineering
  2. Analysis economics
  3. Management of the project
  4. Estimation and management of costs

Regarding your technical document, which is mandatory for registering for the Certified Cost Professional Examination (CCP), your trainers will advise you on suitable subjects and help you develop a solid foundation. They will also assess your work and offer comments when ready. The teachers will also verify that your paper is prepared in accordance with AACE criteria so that the examining body of AACE approves it.

Kryterion acts as a certified test proof for the Certified Cost Professional (CCP) exam with testing sites throughout the globe. You may take your computer-based test every day and whenever you want.

 

Updated Verified CCP Q&As – Pass Guarantee: https://www.trainingdump.com/AACE-International/CCP-practice-exam-dumps.html

Updated PDF (New 2022) Actual AACE International AACE-PSP Exam Questions [Q17-Q41]

Updated PDF (New 2022) Actual AACE International AACE-PSP Exam Questions

Verified AACE-PSP Exam Dumps PDF [2022] Access using TrainingDump

What is the duration, language, and format of the Planning & Scheduling Professional (PSP) Exam

  • Total questions: 119
  • Passing score: 70%
  • Duration of Exam: 5 hours
  • Format: Multiple choice, compound, scenario questions + 1 memo writing assignment
  • Language of Exam: English

How to Prepare For Planning & Scheduling Professional (PSP) Exam

Preparation Guide for Planning & Scheduling Professional (PSP) Exam

Introduction

The Planning & Scheduling Professional PSP exam test is administered by AACE International, the Association for the Advancement of Cost Engineering. In 1956, during the organizational meeting of the American Association of Cost Engineering at the University of New Hampshire in Durham, New Hampshire, 59 cost estimators, and cost engineers founded AACE International (Association for the Advancement of Cost Engineering). The International Headquarters of AACE is based in Morgantown, West Virginia, USA. AACE is a specialized non-profit organization. The Board of the Council of Engineering and Technical Specialty Boards (CESB) is a member of AACE International.

AACE operates eight qualification programs at present. Both include the agreement and passing of an evaluation to adhere to a canon of ethics. Most require previous experience in the industry and may provide recertification through continuing education or reexamination. Six of these certifications are accredited by the Council of Engineering and Scientific Specialty Boards (CESB).

This exam guide is intended to aid in achieving AACE’s specialty certification with the best possible grades. It will enable you to understand the scope of the Planning & Scheduling Professional (PSP) Exam and help you to prepare for it successfully by making use of the provided PSP exam dumps. This guide includes information on the certification test target audience, recommended preparation and documentation, and a full list of exam targets, all to help you obtain a passing grade. To increase your chances of passing the test, AACE strongly recommends a mix of on-the-job experience, course attendance, and self-study, and taking the PSP practice exams. This guide contains useful references for detailed knowledge.

 

Please go to Updated PDF (New 2022) Actual AACE International AACE-PSP Exam Questions [Q17-Q41] to view the test

Try Best AACE-PSP Exam Questions from Training Expert TrainingDump: https://www.trainingdump.com/AACE-International/AACE-PSP-practice-exam-dumps.html

[Jan-2022] AACE International CCP Actual Questions and Braindumps [Q33-Q53]

[Jan-2022] AACE International CCP Actual Questions and Braindumps

Pass CCP Exam with Updated CCP Exam Dumps PDF 2022

For more info read reference

Official Website

How much AACE-International CCP: Certified Cost Professional (CCP) Exam Cost

The costs of this examination vary and according to area in which you are requesting and when you apply on the website of the AACE and go to the payments section, the precise number of the examination is accessible. In general, it costs about USD 200. Click the Apply now button on the official AACE website and select a region for additional price information. There may also be other expenses such as the purchase of CCP exam dumps and subsequently the examination by means of CCP practice exams. If you have or apply for an AACE membership, certificates are given to you at reduced rates.

AACE-International CCP: Certified Cost Professional (CCP) Exam Certification Path

Certified Cost Professional (CCP) Examination comprises solely of the AACE-International CCP: Certified Cost Professional Examination (CCP). Certified Cost Professional Examination (CCP). The candidates must meet the qualifying requirements for a minimum of eight years of industry experience or four years of industry experience and four years of associated academic degree. Those who have certification as a Certified Cost Professional (CCP) must recertification each Three years after the date on which they were first certified. Certification holders must have at least 15 recertification units during a 3-year period to be eligible for recertification. The studying guide, AACE’s Suggested Approaches, AACE’s Fundamentals & Understanding of Cost Engineering and AACE’s Total Cost Managing Framework will be given in CCP exam dumps. You will also be provided with unique documents from our certified professionals.

The emphasis is on fundamental statistical, economic and financial understanding. In order to assess the differences between two or more alternative actions, you will be given with the necessary components to comprehend economic cost, such as inflation, depreciation, escalation, governmental cost effects, etc. You will also concentrate on systems engineering and get acquainted with methods that help solve major engineering issues. You will also learn how statistical data and probability may help you to examine data to make conclusions. The material of the course will be shown through practical examples. Several activities and tests are provided in order to put your newly learned information into practice straightaway. CCP exam dumps include all this preparation material.

 

Please go to [Jan-2022] AACE International CCP Actual Questions and Braindumps [Q33-Q53] to view the test

Latest CCP Pass Guaranteed Exam Dumps with Accurate & Updated Questions: https://www.trainingdump.com/AACE-International/CCP-practice-exam-dumps.html