Pass Exam Questions Efficiently With PMI-RMP Questions (2025) [Q51-Q73]

Pass Exam Questions Efficiently With PMI-RMP Questions (2025) [Q51-Q73]

Rate this post

Pass Exam Questions Efficiently With PMI-RMP Questions (2025) 

PMI-RMP Questions – Truly Beneficial For Your PMI Exam 

NO.51 When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?

 
 
 
 

NO.52 During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?

 
 
 
 

NO.53 The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?

 
 
 
 

NO.54 The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.

 
 
 
 

NO.55 The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

 
 
 
 
 

NO.56 A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

 
 
 
 

NO.57 Examine the figure given below. What will be the expected monetary value of Risk C?

 
 
 
 

NO.58 Ted is the project manager of the HRR project for his company. Management has asked that Ted periodically reviews the contingency reserve as risk events happen, pass, or are still pending.
What is the purpose of reviewing the contingency reserve?

 
 
 
 

NO.59 In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.
Which technique is the risk manager using?

 
 
 
 

NO.60 Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?

 
 
 
 

NO.61 You are the project manager of the AMD project for your organization. In this project, you are currently performing quantitative risk analysis. The tool and technique you are using is simulation where the project model is computed many times with the input values chosen at random for each iteration. The goal is to create a probability distribution from the iterations for the project schedule.
What technique will you use with this simulation?

 
 
 
 

NO.62 A project manager is creating a risk management plan. The project sponsor does not see the need for additional risk management, believing that the only risks to the project are financial risks.
What procedure could the project manager use to identify other potential topics such as technical, quality, performance, project, management, internal and external risks?

 
 
 
 

NO.63 You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders’ approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?

 
 
 
 

NO.64 You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders – including management. You will need to update all of the following information except for which one?

 
 
 
 

NO.65 When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

 
 
 
 
 

NO.66 Your project spans the entire organization. You would like to assess the risk of the project but are worried that some of the managers involved in the project could affect the outcome of any risk identification meeting. Your worry is based on the fact that some employees would not want to publicly identify risk events that could make their supervisors look bad. You would like a method that would allow participants to anonymously identify risk events. What risk identification method could you use?

 
 
 
 

NO.67 The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?

 
 
 
 

NO.68 A well established project begins to experience cost overruns and falls behind schedule. The project risk register identifies many risks and risk response plans in place, yet many risks are transitioning into issues. As the risks occur and become issues, many of the response plans are in progress, but not complete. The data from this graph represents the status of the project risks.

Based on this information, what improvement to the risk management process is required?

 
 
 
 

NO.69 Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?

 
 
 
 

NO.70 You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?

 
 
 
 

NO.71 The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.
The project manager would like the risk manager to take full advantage of opportunities.
Which response should the risk manager take?

 
 
 
 

NO.72 A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)

 
 
 
 
 

NO.73 A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

 
 
 
 

Truly Beneficial For Your PMI Exam: https://www.trainingdump.com/PMI/PMI-RMP-practice-exam-dumps.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below